BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 8 Question 26 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 26
Topic #: 8
[All PMI-SP Questions]

You are the project manager of the HGH Project. Thomas, your project sponsor, asked you to submit

status reports every week, but now he wants you to submit the status reports every other week.

What project management plan would you need to update to reflect this change

from Thomas?

Show Suggested Answer Hide Answer
Suggested Answer: C

The communications management plan needs to be updated whenever there is a

change in the frequency, type, or audience of

communication.

The communication management plan is a document that contains information that is required by

the stakeholders. It also documents when

and how the information should be distributed. It describes the information delivery needs, its

format and level of detail. The communication

management plan is contained in or is a subsidiary of the project management plan.

Answer option D is incorrect. The project management plan is a collection of subsidiary plans,

including the communications management plan.

Answer option A is incorrect. The scope of the project is not being changed in this example, so there

is no need to update the plan.

Answer option B is incorrect. There is no plan by the name of performance management plan, so this

choice is incorrect.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel