Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 7 Question 63 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 63
Topic #: 7
[All PMI-SP Questions]

You are creating a status report to show how your project is progressing. Management is interested in several key activities and their status. You need to report work performance information to management. All of the following are example of work performance information you should include in your report except for which one?

Show Suggested Answer Hide Answer
Suggested Answer: B

information. Management is interested in the how well the project

is performing, what activities are currently underway, and what's been completed to date.

Answer option A is incorrect the project's performance on schedule should be reported

Answer option C is incorrect as management is interested in what activities have been started and

finished.

Answer option D is incorrect as management does want to know the percent of completion for the

in-progress activities


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel