Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 7 Question 6 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 6
Topic #: 7
[All PMI-SP Questions]

What project management plan will document the time frame and frequency for the distribution of required information?

Show Suggested Answer Hide Answer
Suggested Answer: B

The project's Communications Management Plan defines what information will be distributed, when

it will be distributed, to whom it will be

distributed, and the modality of the information.

Answer option D is incorrect. The Schedule Management Plan defines the project work, when the

project work will happen, resource

utilization, and how the schedule will be monitored and controlled.

Answer option C is incorrect. There is a stakeholder management strategy, but not a Stakeholder

Management Plan.

Answer option A is incorrect. The project's Scope Management Plan defines how the scope will be

created, how the changes will be allowed,

how the scope will be executed, monitored and controlled, and finally closed.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel