BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 7 Question 59 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 59
Topic #: 7
[All PMI-SP Questions]

You are the project manager for your organization. You have created the project schedule and have

presented it to the management for their

approval. Management decides to enforce resource leveling heuristics on your project schedule.

What will likely happen to your project now?

Show Suggested Answer Hide Answer
Suggested Answer: C

Resource leveling heuristics limits the amount of time a resource is allowed to work in a

given time period. This action typically increases the

project duration. By adding additional resources to effort-driven activity the project can still

complete, often, in the same schedule, otherwise

the duration of the project will increase.

Answer option B is incorrect. Resource leveling heuristics does not change the project scope.

Answer option A is incorrect. This is not an instance of cutting the project scope.

Answer option D is incorrect. The project scope baseline is not affected by resource leveling

heuristics.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel