You are the project manager for your organization. You have created the project schedule and have
presented it to the management for their
approval. Management decides to enforce resource leveling heuristics on your project schedule.
What will likely happen to your project now?
Resource leveling heuristics limits the amount of time a resource is allowed to work in a
given time period. This action typically increases the
project duration. By adding additional resources to effort-driven activity the project can still
complete, often, in the same schedule, otherwise
the duration of the project will increase.
Answer option B is incorrect. Resource leveling heuristics does not change the project scope.
Answer option A is incorrect. This is not an instance of cutting the project scope.
Answer option D is incorrect. The project scope baseline is not affected by resource leveling
heuristics.
Currently there are no comments in this discussion, be the first to comment!