You work as the project manager for BlueWell Inc. Mark, a project team member, has some doubts

related to the outputs of the control

schedule process. Which of the following is an output of the control schedule process?

Show Suggested Answer Hide Answer
Suggested Answer: C

Only change request is a valid answer. The five outputs of the control schedule process

are work performance measurements, organizational

process assets updates, change requests, the project management plan updates, and project

document updates.

Change requests are requests to expand or reduce the project scope, modify policies, processes,

plans, or procedures, modify costs or

budgets or revise schedules. These requests for a change can be direct or indirect, externally or

internally initiated, and legally or contractually

imposed or optional. A Project Manager needs to ensure that only formally documented requested

changes are processed and only approved

change requests are implemented.

Answer option D is incorrect. Activity resource requirement is not an output of the control schedule

process.

Answer option A is incorrect. The project schedule is not an output of the control schedule process.

Answer option B is incorrect. Lessons learned is not an output of the control schedule process.