You work as the project manager for BlueWell Inc. Mark, a project team member, has some doubts
related to the outputs of the control
schedule process. Which of the following is an output of the control schedule process?
Only change request is a valid answer. The five outputs of the control schedule process
are work performance measurements, organizational
process assets updates, change requests, the project management plan updates, and project
document updates.
Change requests are requests to expand or reduce the project scope, modify policies, processes,
plans, or procedures, modify costs or
budgets or revise schedules. These requests for a change can be direct or indirect, externally or
internally initiated, and legally or contractually
imposed or optional. A Project Manager needs to ensure that only formally documented requested
changes are processed and only approved
change requests are implemented.
Answer option D is incorrect. Activity resource requirement is not an output of the control schedule
process.
Answer option A is incorrect. The project schedule is not an output of the control schedule process.
Answer option B is incorrect. Lessons learned is not an output of the control schedule process.