Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 7 Question 49 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 49
Topic #: 7
[All PMI-SP Questions]

What is the formula to find the schedule performance index?

Show Suggested Answer Hide Answer
Suggested Answer: C

The schedule performance index shows how well the project is performing on schedule.

It is found by dividing the earned value by the

planned value.

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that

the schedule is ahead or behind what

was planned for this period in time. The schedule variance is calculated based on the following

formula:

SV = Earned Value (EV) - Planned Value (PV)

If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater

than 0 shows that the project is ahead of

the planned schedule. A value of 0 indicates that the project is right on target.

Answer option D is incorrect. EV-AC is the project's cost variance.

Answer option B is incorrect. EV/AC is the project's cost performance index.

Answer option A is incorrect. EV-PV is the project's schedule variance.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel