Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 7 Question 11 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 11
Topic #: 7
[All PMI-SP Questions]

Cathy is the project manager of the NNQ Project. She currently has completed 45 percent of the project but was scheduled to have 65 percent of the project completed. This project has a budget of $344,000 and was scheduled to last four months. Cathy has spent $198,998 to date on the project. Based on this information, what is the estimate at completion for the NNQ Project?

Show Suggested Answer Hide Answer
Suggested Answer: C

The estimate at completion (EAC) formula is the Budget at Completion (BAC)/Cost

Performance Index (CPI). In this instance, the CPI is .78 and

the BAC is $344,000. Cathy's project isn't doing too well.

Answer option D is incorrect. This value represents the estimate to complete for the project.

Answer option B is incorrect. This value represents the negative cost variance.

Answer option A is incorrect. This value represents the negative value the project will have once all

the work is completed.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel