Tom is the project manager of the HQQ Project. His project has a schedule variance of -$34,500 due to some errors early in the project. Management would like to know how Tom will respond to these variances. What action can help Tom to manage the errors in the project and to ensure that the errors would not occur again?
An activity is an individual element of work that is logically linked to other activities to
form the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, material, and equipment), as well as a start and
completion date that is tied to a work calendar. It also has a relationship with other activities
(predecessors and successors).
Carolynn
2 months agoCasie
4 days agoMaurine
10 days agoEvangelina
22 days agoSusana
29 days agoCherilyn
2 months agoLisandra
22 days agoTomoko
28 days agoLuis
1 months agoPaulina
2 months agoPatrick
3 months agoAlfred
2 months agoJacquelyne
2 months agoJohnna
3 months agoNaomi
3 months agoGermaine
3 months agoRickie
3 months ago