Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:
If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?
Shawnee
6 months agoHyman
6 months agoTracie
7 months agoPedro
7 months agoNieves
5 months agoDorathy
6 months agoMaybelle
6 months agoPete
6 months agoHyman
7 months agoMarvel
7 months agoEdison
7 months agoArlene
6 months agoTamesha
6 months agoVerona
7 months agoRoslyn
7 months agoGerman
7 months ago