Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:
If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?
Shawnee
8 months agoHyman
8 months agoTracie
8 months agoPedro
8 months agoNieves
6 months agoDorathy
7 months agoMaybelle
7 months agoPete
7 months agoHyman
8 months agoMarvel
8 months agoEdison
8 months agoArlene
7 months agoTamesha
7 months agoVerona
8 months agoRoslyn
8 months agoGerman
8 months ago