Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 6 Question 80 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 80
Topic #: 6
[All PMI-SP Questions]

You are the project manager for your company. You are currently working with your project team to begin sequencing the activity list. You will need organizational process assets and four other documents as inputs to this process. Which of the following is NOT one of the four documents you will need for activity sequencing?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel