BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 6 Question 56 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 56
Topic #: 6
[All PMI-SP Questions]

You are the project manager for your organization. You are working with your project team to create the schedule baseline for your project. You will also be creating the schedule data for this project. The schedule data typically includes all of the following except for which one?

Show Suggested Answer Hide Answer
Suggested Answer: A

Risk activities are not part of the schedule data. Risk is documented in the risk register,

and monitored and controlled throughout the project.

In some instances, risk may be part of the activity attributes. The schedule data includes the

schedule milestones, schedule activities, activity

attributes, and the assumptions and constraints.

The schedule data includes the schedule activities, schedule milestones, activity attributes, and

documentation of all known assumptions and

constraints. The sum of additional data varies by application area. The schedule data commonly

supplied as supporting details includes:

Resource requirement by time period, frequently in the category of histogram

Alternative schedules, such as best case or worst case, or resource leveled, with or without imposed

dates

Scheduling of contingency reserves

Answer option D is incorrect. Schedule milestones are part of the schedule data.

a

Answer option B is incorrect. Schedule activities are part of the schedule data.

Answer option C is incorrect. Activity attributes are part of the schedule data.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel