BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 6 Question 32 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 32
Topic #: 6
[All PMI-SP Questions]

You are the project manager of the NHA Project. This project is expected to last one year with

quarterly milestones throughout the year. Your project is supposed to be at the third milestone

today, but you are likely to be only 60 percent complete. Your project has a BAC of $745,000 and you

have spent $440,000 of the budget-to-date. What is your schedule variance for this project?

Show Suggested Answer Hide Answer
Suggested Answer: D

The schedule variance is found by subtracting the planned value from the earned value.

In this instance, it is $447,000 minus $558,750.

Schedule variance (SV) is a measure of schedule performance on a project. The variance notifies that

the schedule is ahead or behind what

was planned for this period in time. The schedule variance is calculated based on the following

formula:

SV = Earned Value (EV) - Planned Value (PV)

If the resulting schedule is negative, it indicates that the project is behind schedule. A value greater

than 0 shows that the project is ahead of

the planned schedule. A value of 0 indicates that the project is right on target.

Answer option C is incorrect. $7,000 is the cost variance for this project.

Answer option A is incorrect. $11,667 is the variance at completion for this project.

Answer option B is incorrect. 1.02 is the cost performance index for this project.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel