BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 6 Question 10 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 10
Topic #: 6
[All PMI-SP Questions]

Maurice is the project manager of the NHQ Project and his project team has just finished the project activities. The quality control team reports that the project deliverables are perfect. The only thing left to in the project is to verify scope. This process will be performed by the project stakeholders. Maurice is required to submit a final project report and report on the project performance. Maurice's project had a budget of $234,000 but the project spent $245,000. In the final report management wants to know the project's cost performance index (CPI). What value should Maurice report?

Show Suggested Answer Hide Answer
Suggested Answer: B

Cost performance index (CPI) is used to calculate performance efficiencies. It is used in

trend analysis to predict future performance. CPI is the

ratio of earned value to actual cost. The CPI is calculated based on the following formula:

CPI = Earned Value (EV) / Actual Cost (AC)

If the CPI value is greater than 1, it indicates better than expected performance, whereas if the value

is less than 1, it shows poor

performance. The CPI value of 1 indicates that the project is right on target. In this instance, the

earned value is $234,000 as the project

work is 100 percent. The actual costs are $245,000.

Answer option D is incorrect. This is the schedule performance index value.

Answer option A is incorrect. This is the variance at completion for the project.

Answer option C is incorrect. There is enough information to find the answer.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel