Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 5 Question 91 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 91
Topic #: 5
[All PMI-SP Questions]

You are the project manager of the NHL Project for your organization. You are working with your project team to create the schedule baseline for this project. According to you, which of the following statements describes how the schedule baseline is created?

Show Suggested Answer Hide Answer
Suggested Answer: B

Your schedule variance is -$33,750. You can find this by using the formula earned value-

minus planned.

Answer option C is incorrect. Cost is not the largest variance in the project.

Answer option A is incorrect. Cost is not the largest variance in the project (it is -$8,000).

Answer option D is incorrect. -$20,000 is the variance at completion for the project.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel