You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project's budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?
Your schedule variance is -$33,750. You can find this by using the formula earned value-
minus planned.
Answer option C is incorrect. Cost is not the largest variance in the project.
Answer option A is incorrect. Cost is not the largest variance in the project (it is -$8,000).
Answer option D is incorrect. -$20,000 is the variance at completion for the project.
Shalon
3 months agoVonda
3 months agoSheldon
2 months agoArgelia
2 months agoVivienne
2 months agoElinore
2 months agoEstrella
2 months agoJerry
2 months agoGlenn
3 months agoLoreta
4 months agoChaya
4 months agoColton
3 months agoTaryn
3 months agoDyan
3 months agoDevon
4 months agoCasey
4 months agoCyril
2 months agoLettie
3 months agoPaulina
3 months agoLigia
3 months agoLoreta
4 months ago