You are the project manager of the GHY project. Your project has a BAC of $675,000 and is forty percent complete though you were supposed to be forty-five percent complete. Due to some errors early in the project, you had to spend $278,000 of your project's budget to reach this point. Management is asking for a variance report. What part of your project has the largest variance?
Your schedule variance is -$33,750. You can find this by using the formula earned value-
minus planned.
Answer option C is incorrect. Cost is not the largest variance in the project.
Answer option A is incorrect. Cost is not the largest variance in the project (it is -$8,000).
Answer option D is incorrect. -$20,000 is the variance at completion for the project.
Shalon
4 months agoVonda
4 months agoSheldon
3 months agoArgelia
3 months agoVivienne
3 months agoElinore
3 months agoEstrella
3 months agoJerry
3 months agoGlenn
4 months agoLoreta
5 months agoChaya
5 months agoColton
4 months agoTaryn
4 months agoDyan
4 months agoDevon
5 months agoCasey
5 months agoCyril
4 months agoLettie
4 months agoPaulina
4 months agoLigia
4 months agoLoreta
5 months ago