You work as a project manager for BlueWell Inc. Some of the activities in your project are not being completed on time. You reviewed these activities with your project team and discovered that the time estimates for the project are much more aggressive than what they are actually experiencing in the completion of the activities. You elect to create a new schedule for the project. What project anagement process are you working with when you create a new target schedule?
In severe cases, new schedule duration estimates with new forecasted start and finish
dates are needed. In these instances, it is an example
of using the control schedule process.
Control schedule process is a method of monitoring the status of the project to update project
progress and deal with the changes to the
schedule baseline. It is concerned with:
Determining the current status of the project
Influencing the factors that create schedule changes
Determining that the project schedule has changed
Managing the actual changes as they occur
Control schedule is a component of the Perform Integration Change Control process.
Answer option D is incorrect. The activity resources would only address the addition or replacement
of resources needed to complete the
project work.
Answer option B is incorrect. This is a tempting choice, but new schedules are a part of the control
schedule process.
Answer option A is incorrect. Develop schedule is not the best choice for this question.
Flo
2 months agoGlen
2 months agoMicaela
2 months agoElinore
1 months agoAudry
1 months agoMireya
2 months agoFallon
2 months agoTiera
2 months agoMirta
2 months agoKris
2 months agoMakeda
2 months agoRaul
3 months agoFelix
2 months agoKirby
2 months agoCandida
2 months agoCyndy
2 months agoHoney
3 months agoAnnamae
3 months agoStephen
2 months agoProvidencia
2 months ago