BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 5 Question 85 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 85
Topic #: 5
[All PMI-SP Questions]

You work as a project manager for Honeywell Inc. You have been distributing performance information, including status reports, progress measurement, and forecasts to various stakeholders. A trainee of this company wants to know what are the inputs for generating performance reports. Which of the following are the necessary inputs? Each correct answer represents a part of the solution. Choose two.

Show Suggested Answer Hide Answer
Suggested Answer: B, C

According to the scenario, you can use the following inputs in order to generate

performance reports:

WPI: Work performance information is the data gathered on the status of the project schedule

activities that are performed to

accomplish the project work. This data is collected as part of the Direct and Manage Project

Execution processes. WPI includes the

following:

Deliverables status

Schedule Progress

Costs incurred

WPM: Work performance measurements are created from the work performance information.

WPMs are an output of Control schedule,

Control cost, and Control scope processes, which are monitoring and controlling processes. WPMs

consist of planned versus actual

performance indicators with respect to scope, schedule, and cost. They are documented and

communicated to the stakeholders and are

used to make project activity metrics, such as the following:

Planned vs. Actual Technical performance and Scope performance

Planned vs. Actual Schedule performance

Planned vs. Actual Cost performance

Answer option A is incorrect. Variance analysis is an after-look at what caused a difference between

the baseline and the actual performance.

It is one of the tools and techniques used for report performance.

Answer option D is incorrect. Change requests are requests to expand or reduce the project scope,

modify policies, processes, plans, or

procedures, modify costs or budgets or revise schedules. These requests for a change can be direct

or indirect, externally or internally

initiated, and legally or contractually imposed or optional. A Project Manager needs to ensure that

only formally documented requested

changes are processed and only approved change requests are implemented.


Contribute your Thoughts:

Michel
2 months ago
Woah, this is a tough one! Let's see, I'm gonna go with A and C. Variance analysis is a must, and WPI is the secret sauce that'll make your reports shine. Trust me, I'm a professional. *wink*
upvoted 0 times
...
Hubert
2 months ago
A and D, without a doubt. Variance analysis is the bread and butter, and change requests are the spice of life. You can't have a proper report without those two.
upvoted 0 times
Josefa
18 days ago
Sorry, but those are not the necessary inputs for generating performance reports.
upvoted 0 times
...
Francoise
20 days ago
B) WPM
upvoted 0 times
...
Kendra
22 days ago
C) WPI
upvoted 0 times
...
Sharmaine
29 days ago
Exactly! Those are the key inputs for generating performance reports.
upvoted 0 times
...
Nell
1 months ago
D) Change request
upvoted 0 times
...
Sylvia
1 months ago
A) Variance analysis
upvoted 0 times
...
...
Sue
2 months ago
Hold up, I smell a trick question here. A and D, for sure. Variance analysis is a classic, and change requests can make or break your project performance. The other options are just red herrings.
upvoted 0 times
...
Alpha
2 months ago
B and C, baby! WPM and WPI are the real deal. Forget the rest, this is the dynamic duo you need for your reports. *mic drop*
upvoted 0 times
Filiberto
16 days ago
D) Change request
upvoted 0 times
...
Flo
18 days ago
C) WPI
upvoted 0 times
...
Lauran
1 months ago
B) WPM
upvoted 0 times
...
Ty
1 months ago
A) Variance analysis
upvoted 0 times
...
...
Paola
2 months ago
I think WPM is not necessary for generating performance reports.
upvoted 0 times
...
Raina
2 months ago
I believe change request is also an input for generating performance reports.
upvoted 0 times
...
Diego
2 months ago
Hmm, I'd say A and D. Change requests are a crucial input, because they can impact project performance. And variance analysis is a no-brainer.
upvoted 0 times
Paola
1 months ago
Yes, you're correct. Change requests can have a big impact on project performance, and variance analysis helps us understand how we're tracking against our plan.
upvoted 0 times
...
Eleonore
2 months ago
I think you're right. Change requests and variance analysis are definitely important inputs for generating performance reports.
upvoted 0 times
...
...
Albert
2 months ago
I agree with Cyril. Variance analysis and WPI are important for performance reports.
upvoted 0 times
...
Cyril
2 months ago
I think the inputs for generating performance reports are variance analysis and WPI.
upvoted 0 times
...
Angelyn
3 months ago
A and C, of course! You need variance analysis to track progress and WPI to measure performance. Those are the must-have inputs for any decent project report.
upvoted 0 times
Ceola
2 months ago
C) WPI
upvoted 0 times
...
Sue
2 months ago
A) Variance analysis
upvoted 0 times
...
...

Save Cancel