Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 5 Question 75 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 75
Topic #: 5
[All PMI-SP Questions]

You are the project manager of a project that has a budget of $875,000 and you have completed 40 percent of the project work. Due to some errors, however, you have actually spent $425,000 of the budget. Management wants to know what the project's cost performance index is. What value do you report?

Show Suggested Answer Hide Answer
Suggested Answer: D

Beth, the project manager, is responsible for communication with all stakeholders. According to the

PMBOK, the project manager occupies the

center of the interactions between stakeholders and the project itself.

Answer option B is incorrect. Sarah may help with the communications, but she is not responsible

for the communications.

Answer option A is incorrect. Thomas, the project sponsor, just needs to be kept abreast of the

information.

Answer option C is incorrect. The project team leaders for the virtual sites are not responsible for

communicating with the project

stakeholders.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel