Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 5 Question 70 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 70
Topic #: 5
[All PMI-SP Questions]

Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:

If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Tiffiny
8 months ago
I don't know, guys. If the project schedule is fixed, then the delay might not impact the end date at all. Maybe the answer is A?
upvoted 0 times
...
Lamar
8 months ago
Okay, let's think this through. If Stephen is two days late on Activity B, that means the entire project will be delayed by two days, right? So, the answer must be C.
upvoted 0 times
...
Scarlet
8 months ago
Hmm, let's take a closer look at the diagram. Activity B is on the critical path, so any delay in that activity will directly affect the project end date.
upvoted 0 times
Phung
8 months ago
The project will be late by two days if Stephen is two days late.
upvoted 0 times
...
Darrel
8 months ago
Stephen's delay will impact the project end date.
upvoted 0 times
...
Andree
8 months ago
Activity B is on the critical path.
upvoted 0 times
...
...
Whitley
8 months ago
Ah, this is a tricky one! The project schedule is fixed, so we need to carefully analyze the impact of Stephen's delay on the critical path.
upvoted 0 times
...

Save Cancel