BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 5 Question 38 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 38
Topic #: 5
[All PMI-SP Questions]

You work as a scheduler for your organization. You are developing a schedule and its constraints for

the SAP project. There are nine inputs to develop a project schedule. Which of the following is NOT

an input to the schedule development process?

Show Suggested Answer Hide Answer
Suggested Answer: A

The WBS is not an input, directly, to the develop schedule process. Technically, you will

need the scope baseline, which does include the WBS.

The inputs in developing a schedule process are of nine types, which are as follows:

Activity list

Activity attributes

Project schedule network diagrams

Activity resource requirements

Resource calendars

Activity duration estimates

Project scope statement

Enterprize environmental factors

Organization process assets


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel