BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 5 Question 33 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 33
Topic #: 5
[All PMI-SP Questions]

You are the project manager of the NHQ project. Your project has a budget of $1,258,456, and is

scheduled to last for three years. Your project is currently forty percent complete though it should

be forty-five percent complete. In order to reach this point of the project, you have spent $525,000.

Management needs a performance report regarding the NHQ project. Management is concerned

that this project will be over budget upon completion. Management would like to create a report

telling them how much more the project will need to complete. What value should you tell

management?

Show Suggested Answer Hide Answer
Suggested Answer: B

The project will need $787,504 more to complete. This formula, the estimate to

complete, is estimate at completion minus the actual costs.

Here,

CPI = EV/AC =(0.40*1,258,456)/525000= 0.95882, and

ETC = EAC - AC

= (BAC/CPI) - AC

=(1,258,456/0.95882) - 525000

= 1,312,504- 525000

= 787,504

The estimate to complete (ETC) is the expected cost needed to complete all the remaining work for a

scheduled activity, a group of activities,

or the project. ETC helps project managers predict what the final cost of the project will be upon

completion. The formula for the ETC is EAC-

AC. The EAC is BAC/CPI.

Answer option C is incorrect. This is the estimate at completion.

Answer option A is incorrect. This is the planned value.

Answer option D is incorrect. This is not a valid value based on the current project performance.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel