BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 5 Question 27 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 27
Topic #: 5
[All PMI-SP Questions]

You are the project manager for the NHQ project. The management has reminded you that you must

not allocate any project team member for more than 25 hours per work week on your project. This

policy is because your organization is in a weak matrix and the project team members are on several

projects at once within the organization. The 25-hour limit per resource is an example of which one

of the following?

Show Suggested Answer Hide Answer
Suggested Answer: B

The limit on each work is an organizational policy for each project. Policies, rules, and

organizational requirements are the enterprise

environmental factors.

Answer option D is incorrect. Organizational process assets are things that have been created for the

project manager, such as software,

templates, guidelines, and other resources that will assist the project manager in completing the

project.

Answer option C is incorrect. While this could be a resource limitation, it is not a valid project

management term. Resource leveling heuristics

or a project constraint would have been acceptable answers.

Answer option A is incorrect. Expert judgment happens, when the project manager relies on

someone with more knowledge on a topic to help

the project manager make the best project decision.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel