You are the project manager for the NHQ project. The management has reminded you that you must
not allocate any project team member for more than 25 hours per work week on your project. This
policy is because your organization is in a weak matrix and the project team members are on several
projects at once within the organization. The 25-hour limit per resource is an example of which one
of the following?
The limit on each work is an organizational policy for each project. Policies, rules, and
organizational requirements are the enterprise
environmental factors.
Answer option D is incorrect. Organizational process assets are things that have been created for the
project manager, such as software,
templates, guidelines, and other resources that will assist the project manager in completing the
project.
Answer option C is incorrect. While this could be a resource limitation, it is not a valid project
management term. Resource leveling heuristics
or a project constraint would have been acceptable answers.
Answer option A is incorrect. Expert judgment happens, when the project manager relies on
someone with more knowledge on a topic to help
the project manager make the best project decision.