You are the project manager of the GUH project. You are using the critical chain scheduling method as your approach to project scheduling. What two items can you compare in the critical chain method to determine if corrective action is appropriate?
The difference between the buffer needed and the buffer remaining can determine
whether corrective action is appropriate.
Answer option C is incorrect. This is not an accurate description of how the critical chain determines
the need for corrective action.
Answer option B is incorrect. This is not an accurate description of how the critical chain determines
the need for corrective action.
Answer option A is incorrect. This is not an accurate description of how the critical chain determines
the need for corrective action.