Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 4 Question 88 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 88
Topic #: 4
[All PMI-SP Questions]

You are the project manager for your company. You are working with the management regarding the exact end date of your project. Management needs to know what day of the week your project will complete. Assuming that your project will not require any work to be completed over the upcoming weekends and that the remaining project work will commence on a Tuesday, what day of the week will the project end if there are 67 days of project work left to complete?

Show Suggested Answer Hide Answer
Suggested Answer: D

Stakeholders are interviewed and can help identify other stakeholders that should be

included in the project communications.

Answer option B is incorrect. According to the PMBOK, this is not the best answer.

Answer option A is incorrect. Stakeholders are entered into a stakeholder register, not identified by

it.

Answer option C is incorrect. Project customers are stakeholders.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel