Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 4 Question 76 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 76
Topic #: 4
[All PMI-SP Questions]

Examine the figure given below.

In this project network diagram, what is the total float for Activity I?

Show Suggested Answer Hide Answer
Suggested Answer: A

The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for

Activity I is Day 20. Therefore, the difference of

the early start and the late start reveals the float as three days. It is possible, and acceptable, to use

the difference of the early finish and the late finish to find the float, as the value will be the same

amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total

float.


Contribute your Thoughts:

Jillian
6 months ago
Interesting. I guess I'll go with C) Five. It's just a gut feeling.
upvoted 0 times
...
Nina
6 months ago
I'm leaning towards B) Zero. It seems like there's no extra time for Activity I.
upvoted 0 times
...
Jonell
7 months ago
I disagree. I believe the answer is D) One, but I'm not sure.
upvoted 0 times
...
Elise
7 months ago
I think the answer is A) Three.
upvoted 0 times
...
Micaela
7 months ago
Yeah, it's tricky. Especially calculating the float for Activity I.
upvoted 0 times
...
Jillian
7 months ago
Did you see the question about the project network diagram?
upvoted 0 times
...

Save Cancel