Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 4 Question 7 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 7
Topic #: 4
[All PMI-SP Questions]

You are the project manager of the GHY Project. This project is scheduled to last for one year and has a BAC of $4,500,000. You are currently 45 percent complete with this project, though you are supposed to be at your second milestone, which accounts for half of the project completion. There have been some errors in the project, which has caused you to spend $2,073,654. What is this project's planned value?

Show Suggested Answer Hide Answer
Suggested Answer: D

The planned value is the worth of the project if it were on time. In this instance, the

project should be 50 percent complete, so the planned

value is half of the project budget - $2,250,000.

Planned value (PV) is the authorized budget assigned to the schedule work to be accomplished for a

schedule activity or work breakdown

structure component. It serves as a baseline against which actual performance is measured. The

theory of planned value is of vital importance

to the project management team and it is important to keep careful track of this. The term planned

value can also be in some situations

referred to by the project management team and the project management team leader as the

budgeted cost of work scheduled (BCWS).

Answer option C is incorrect. This is the budget at completion.

Answer option A is incorrect. This is the earned value for the project.

Answer option B is incorrect. There is enough information to know.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel