BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 4 Question 35 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 35
Topic #: 4
[All PMI-SP Questions]

You are the project manager for GGY Project. You are working with your project team to record the

actual durations for the activities they have

completed in the project schedule. Mary, one of your project team members, wants to know why

you need to know how long it actually took

the project team to complete their assignments as long as the project work is completed. Which of

the following is the best response for

Mary's query?

Show Suggested Answer Hide Answer
Suggested Answer: C

The best answer is to track actual durations to measure the actual progress of the

project.

Actual duration is the time, in the calendar units, between the actual start date of the schedule

activity and either the data date of the project

schedule if the schedule activity is in development or the actual finish date if the schedule activity is

complete.

Answer option B is incorrect. The schedule baseline is not created based on actual durations.

Answer option A is incorrect. Process improvement is part of the quality management knowledge

area, but it is not a reason to track actual

durations.

Answer option D is incorrect. Quality control is the inspection of the project deliverables. It is not

concerned with the actual durations of

project work. The improvement of the project processes is defined in the Process Improvement Plan.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel