Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 4 Question 21 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 21
Topic #: 4
[All PMI-SP Questions]

You are the project manager for your organization. You are coaching Allen, a junior project manager,

on how the details of the project's critical path are calculated. Examine the figure given below:

What is the critical path of this project?

Show Suggested Answer Hide Answer
Suggested Answer: B

The critical path is discovered by summing the duration of each activity node in each

chain of activities in the project network diagram. In this

figure, the critical path is ACFGJ, which is 26 days, the longest chain of activities in the project.

Answer option A is incorrect. This path's duration is 22 days.

Answer option D is incorrect. This path's duration is 23 days.

Answer option C is incorrect. This path's duration is 15 days.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel