Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 4 Question 19 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 19
Topic #: 4
[All PMI-SP Questions]

with an appropriate phrase.

The _______contains the schedule components and the rules for relating and using the components

to represent the process for completing a project.

Show Suggested Answer Hide Answer
Suggested Answer: A

A scheduling tool consists of the schedule components and the rules for connecting and using the

components to characterize

the process for completing a project. It is used to gather the schedule model and provide the means

of adjusting various parameters and

components that are typical in a modeling process.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel