BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 4 Question 18 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 18
Topic #: 4
[All PMI-SP Questions]

with the appropriate word. When activities are logically linked, they become the .

__________

Show Suggested Answer Hide Answer
Suggested Answer: A

An activity is an individual element of work that is logically linked to other activities to

form the schedule. Its primary characteristics include an overall duration based upon the resources

applied to it (manpower, material, and equipment), as well as a start and

completion date that is tied to a work calendar. It also has a relationship with other activities

(predecessors and successors).


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel