Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 3 Question 99 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 99
Topic #: 3
[All PMI-SP Questions]

You have created the project network diagram for your project. Management is reviewing the network diagram and they are curious as to why you have included levels of effort activities as start- to-start and finish-to-finish successor activities for work that uses particular manufacturing equipment. You explained that the levels of effort activities are maintained for the equipment. This relationship and scheduling scenario is also known as what term?

Show Suggested Answer Hide Answer
Suggested Answer: B

The limit on each work is an organizational policy for each project. Policies, rules, and

organizational requirements are the enterprise

environmental factors.

Answer option D is incorrect. Organizational process assets are things that have been created for the

project manager, such as software,

templates, guidelines, and other resources that will assist the project manager in completing the

project.

Answer option C is incorrect. While this could be a resource limitation, it is not a valid project

management term. Resource leveling heuristics

or a project constraint would have been acceptable answers.

Answer option A is incorrect. Expert judgment happens, when the project manager relies on

someone with more knowledge on a topic to help

the project manager make the best project decision.


Contribute your Thoughts:

Stephanie
3 minutes ago
I think the term is Hammock activity.
upvoted 0 times
...

Save Cancel