John works as the project manager for Blue Well Inc. He is identifying the phases within the scope of
work for the project plan. Which of the following can be categorized as a project phase? Each correct
answer represents a complete solution. Choose all that apply.
A phase is a combination of associated activities that represent a distinct stage within a
project. A phase can have distinct start and finish
dates and include several stages of planning and work. Each project has a defined scope of work,
such as a unique product or service. Some
examples of phases within the scope of work for a project plan are conceptual engineering, pre-
construction, and engineering.
Answer option A is incorrect. Concrete is an activity, not a project phase.
Currently there are no comments in this discussion, be the first to comment!