BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 3 Question 42 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 42
Topic #: 3
[All PMI-SP Questions]

John works as the project manager for Blue Well Inc. He is identifying the phases within the scope of

work for the project plan. Which of the following can be categorized as a project phase? Each correct

answer represents a complete solution. Choose all that apply.

Show Suggested Answer Hide Answer
Suggested Answer: B, C, D

A phase is a combination of associated activities that represent a distinct stage within a

project. A phase can have distinct start and finish

dates and include several stages of planning and work. Each project has a defined scope of work,

such as a unique product or service. Some

examples of phases within the scope of work for a project plan are conceptual engineering, pre-

construction, and engineering.

Answer option A is incorrect. Concrete is an activity, not a project phase.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel