Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 3 Question 40 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 40
Topic #: 3
[All PMI-SP Questions]

Jenny works as a Project Manager for Blue Well Inc. She is measuring the schedule efficiency of her project. The key values are provided in the table below: Measurements Values BCWP (or EV)425 BCWS (or PV) 400 ACWP (or AC)510 What is the schedule performance index (SPI) of the project at the current point of time?

Show Suggested Answer Hide Answer
Suggested Answer: C

According to the question, you are required to calculate the schedule performance

index (SPI) of the project. Schedule performance index

(SPI) is the measure of schedule efficiency on a project. It is used in trend analysis to predict future

performance. SPI is the ratio of earned

value to planned value. The SPI is calculated based on the following formula:

SPI = Earned Value (EV) / Planned Value (PV)

If the SPI value is greater than 1, it indicates better than expected performance, whereas if the value

is less than 1, it shows poor

performance. The SPI value of 1 indicates that the project is right on target. Here, SPI is calculated as

follows:

SPI = EV / PV

= 425/400

= 1.0625

As the SPI (1.0625) is greater than 1, it shows that the schedule performance is better than

expected.

What is BCWP (or EV)?

Budgeted cost of work performed (BCWP) or Earned Value (EV) is the value of completed work. It is

the budgeted amount

for the work actually completed on the schedule activity during a given time period.

What is BCWS (or PV)?

Budgeted Cost of Work Scheduled (BCWS) or Planned Value (PV) is the authorized budget assigned

to the scheduled work

to be accomplished for a schedule activity or Work Breakdown Structure (WBS) component.

What is ACWP (or AC)?

Actual cost of work performed (ACWP) or Actual Cost (AC) is the total costs actually incurred and

recorded in accomplishing

work performed during a given time period for a schedule activity. It is the cost of the work to date,

including direct and

indirect costs. AC is money that has actually been expended to date.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel