Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:
If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?
Raylene
1 months agoWillard
1 months agoBrett
1 months agoTheresia
1 months agoJimmie
1 months agoLelia
1 months agoColton
9 days agoJusta
13 days agoBettina
14 days agoShawnna
22 days agoArgelia
22 days agoGeoffrey
30 days agoBrianne
1 months agoMarya
1 months ago