Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 2 Question 94 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 94
Topic #: 2
[All PMI-SP Questions]

The figure given below demonstrates the communications model for a project. What role does component C play in the communication model?

Show Suggested Answer Hide Answer
Suggested Answer: A

An activity is an individual element of work that is logically linked to other activities to

form the schedule. Its primary characteristics include an overall duration based upon the resources

applied to it (manpower, material, and equipment), as well as a start and

completion date that is tied to a work calendar. It also has a relationship with other activities

(predecessors and successors).


Contribute your Thoughts:

Caprice
6 hours ago
I think component C plays the role of the Sender in the communication model.
upvoted 0 times
...

Save Cancel