Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 2 Question 84 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 84
Topic #: 2
[All PMI-SP Questions]

You are the project manager of the HQQ Project. Your project is running late by ten percent of where you should be at this time. Management is concerned and they'd like to know what is your schedule performance index. Considering that the project has a BAC of $567,899, you are thirty percent complete, and you have spent $179,450, what is the SPI for this project?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Lenna
1 days ago
I think the answer is B) 0.75.
upvoted 0 times
...

Save Cancel