Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:
If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?
Beth
4 months agoHerman
5 months agoMarjory
5 months agoDemetra
5 months agoEladia
5 months agoGilberto
5 months agoNicolette
4 months agoVivienne
4 months agoGarry
4 months agoGlendora
5 months agoGeorgiann
5 months agoTherese
5 months agoIluminada
5 months agoIola
5 months agoHarrison
5 months agoJustine
5 months agoEarleen
6 months ago