Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:
If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?
Beth
2 months agoHerman
2 months agoMarjory
2 months agoDemetra
2 months agoEladia
2 months agoGilberto
3 months agoNicolette
1 months agoVivienne
1 months agoGarry
2 months agoGlendora
3 months agoGeorgiann
3 months agoTherese
3 months agoIluminada
2 months agoIola
3 months agoHarrison
3 months agoJustine
3 months agoEarleen
3 months ago