BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 2 Question 84 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 84
Topic #: 2
[All PMI-SP Questions]

Mary is the project manager of the H1QZ Project. This project is a subproject of the HQZ Project and the project schedule is fixed and cannot vary. Stephen, a project team member, reports that he's having trouble completing his project assignment and will likely be at least two days late. Examine the figure given below:

If Stephen's assignment is Activity B, what impact will his two days of lateness have on the project end date?

Show Suggested Answer Hide Answer
Suggested Answer: A

Contribute your Thoughts:

Beth
2 months ago
That's a good point, but based on the fixed schedule in the question, the project will indeed be late by two days.
upvoted 0 times
...
Herman
2 months ago
Bless your heart, Stephen, but your tardiness is going to cost us all. Looks like C is the only logical choice here. Maybe next time, you can try being early for a change!
upvoted 0 times
...
Marjory
2 months ago
But what if we can adjust the schedule to accommodate Stephen's delay?
upvoted 0 times
...
Demetra
2 months ago
I agree with Glendora, Stephen's delay will make the project late by two days.
upvoted 0 times
...
Eladia
2 months ago
I don't know, this just seems like a straightforward critical path analysis. If B is delayed, it has to push the end date back by two days. Simple as that. Option C gets my vote.
upvoted 0 times
...
Gilberto
3 months ago
Two days late, huh? That's like me trying to finish my taxes on time - it ain't happening! But hey, at least the boss can't fire us for being human, right? C is my pick.
upvoted 0 times
Nicolette
1 months ago
Let's hope for the best and that the impact won't be too severe. But yeah, C is the safest bet.
upvoted 0 times
...
Vivienne
1 months ago
Yeah, I agree. It looks like the project will be late by two days if Stephen is delayed.
upvoted 0 times
...
Garry
2 months ago
Don't worry, we all have those days. C does seem like the most likely outcome.
upvoted 0 times
...
...
Glendora
3 months ago
I think the answer is C.
upvoted 0 times
...
Georgiann
3 months ago
Hold up, I'm not so sure about that. Let me take another look at the diagram. Ah, I see now, the project schedule is fixed, so B's delay won't affect the end date. A it is!
upvoted 0 times
...
Therese
3 months ago
Hmm, this looks tricky. Since Activity B is on the critical path, any delay will directly impact the project end date, so I'm going with option C.
upvoted 0 times
Iluminada
2 months ago
Yes, since Activity B is on the critical path, any delay will result in a two-day delay in the project end date.
upvoted 0 times
...
Iola
3 months ago
I agree with you, option C seems to be the most logical choice.
upvoted 0 times
...
...
Harrison
3 months ago
I agree with Justine, the critical path will be impacted.
upvoted 0 times
...
Justine
3 months ago
But the project schedule is fixed, so it will be late by two days.
upvoted 0 times
...
Earleen
3 months ago
I think Stephen's delay will make the project late.
upvoted 0 times
...

Save Cancel