You are the project manager for your company. You are working with the activities defined in the figure below.
What will happen to your project if Activity F takes five additional days to complete than what was expected?
An activity is an individual element of work that is logically linked to other activities to
form the schedule. Its primary characteristics include an overall duration based upon the resources
applied to it (manpower, material, and equipment), as well as a start and
completion date that is tied to a work calendar. It also has a relationship with other activities
(predecessors and successors).
Marti
5 hours ago