Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 2 Question 46 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 46
Topic #: 2
[All PMI-SP Questions]

You are the project manager for the NGH project. The figure given below represents the small

project you are completing for your organization.

How much float can you use on Activity G if Activity B actually takes eight days to complete?

Show Suggested Answer Hide Answer
Suggested Answer: D

If Activity B uses seven days of float, which it can, it does not allow Activity D, G, or J to

have any float available. This is because the total

duration of path ABDGJK cannot exceed 30 days, the duration of the project. If Activity B uses the

seven days of float, then the path meets

the project's duration at Day 30.

Answer options B and A are incorrect. These are not the valid calculation.

Answer option C is incorrect. Seven represents the amount of float available on Activity G before

Activity B uses the available float.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel