Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-SP Topic 2 Question 31 Discussion

Actual exam question for PMI's PMI-SP exam
Question #: 31
Topic #: 2
[All PMI-SP Questions]

Jeff is the project manager of the GHY Project for his organization. He has created the project

network diagram as shown in the figure:

Management is reviewing the network diagram, and they are concerned about the latest date that

Activity I can finish. What is the latest day

Activity I can finish without affecting the project end date?

Show Suggested Answer Hide Answer
Suggested Answer: B

Activity I must finish by Day 22, so that Activity J can start by Day 23. If Activity I finishes

later than Day 22, the project will be late.

Answer option D is incorrect. Day 19 is the earliest Activity I can finish.

Answer option A is incorrect. Day 20 is the latest Activity I can start.

Answer option C is incorrect. Day 17 is the earliest Activity I can start.


Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel