Actual exam question for PMI's PMI-SP exam
Question #: 16
Topic #: 2
[All PMI-SP Questions]

Your project is installing 8,000 light fixtures in a new building. Each of the light fixtures is to be installed exactly the same way but you have discovered that some of the fixtures are installed incorrectly. You and the project team meet and agree to fix the fixtures and to install all future fixtures the same way. This is an example of what executing activity?

Show Suggested Answer Hide Answer
Suggested Answer: D

This is an example of corrective action. The project team will fix the mistake and they

have learned from their mistake so it won't happen again.

Answer option C is incorrect. Risk mitigation is defined as monies spent or actions taken to reduce

the probability and impact of an identified

risk event.

Answer option A is incorrect. A risk response is an action to counteract an identified risk.

Answer option B is incorrect. There may be some team development happening in this instance but

we don't have enough information to know

for certain. Team development is an activity that brings the whole team cohesion, interdependency,

and trust.