Examine the figure given below.
In this project network diagram, what is the total float for Activity I?
The float for Activity I is three days. The early start for Activity I is Day 17 and the late start for
Activity I is Day 20. Therefore, the difference of
the early start and the late start reveals the float as three days. It is possible, and acceptable, to use
the difference of the early finish and the late finish to find the float, as the value will be the same
amount. Answer options B, D, and C are incorrect. These are not the valid calculation for the total
float.
Rolf
7 months agoKenneth
7 months agoTamra
7 months agoKenneth
7 months agoLouisa
8 months agoHerminia
8 months agoMitsue
7 months agoMarlon
8 months agoRoosevelt
8 months agoNida
8 months agoBelen
8 months agoCarma
8 months agoChauncey
8 months agoLindsey
8 months agoNikita
8 months ago