Which of the following is NOT an output of the control schedule process?
The project termination request is not an output of the control schedule. Early
termination of a project is a closing process and usually does
not stem from the project manager.
The outputs of the control schedule process are as follows:
Work Performance Measurements: The work packages and control accounts are documented and
communicated to the stakeholders.
Organizational Process Assets Updates: The assets that are updated are: corrective actions chosen
and the reasons, causes of
variance, and other types of lessons learned from project schedule control.
Change Requests: It is processed for reviews and disposition through the Perform Integrated Change
Control process.
Project Management Plan Updates: The elements that need to be updated are: schedule baseline,
schedule management plan, cost
baseline.
Project Document Updates: The elements that need to be updated in project document updates are:
schedule data and project
schedule.
Von
12 months agoBernadine
1 years agoChuck
1 years agoVeta
1 years agoBeth
11 months agoJonell
11 months agoRasheeda
11 months agoKerry
12 months agoSharen
12 months agoElbert
12 months ago