Which of the following is NOT an output of the control schedule process?
The project termination request is not an output of the control schedule. Early
termination of a project is a closing process and usually does
not stem from the project manager.
The outputs of the control schedule process are as follows:
Work Performance Measurements: The work packages and control accounts are documented and
communicated to the stakeholders.
Organizational Process Assets Updates: The assets that are updated are: corrective actions chosen
and the reasons, causes of
variance, and other types of lessons learned from project schedule control.
Change Requests: It is processed for reviews and disposition through the Perform Integrated Change
Control process.
Project Management Plan Updates: The elements that need to be updated are: schedule baseline,
schedule management plan, cost
baseline.
Project Document Updates: The elements that need to be updated in project document updates are:
schedule data and project
schedule.
Von
11 months agoBernadine
11 months agoChuck
11 months agoVeta
11 months agoBeth
10 months agoJonell
10 months agoRasheeda
10 months agoKerry
10 months agoSharen
10 months agoElbert
10 months ago