Which of the following are the outputs to the Determine Budget process? Each correct answer represents a complete solution. Choose all that apply.
The outputs to the determine budget process are as follows:
Cost performance baseline: The cost performance baseline is an authorized time-phased budget at
completion.
Project funding requirements: The project funding requirements are determined from total funding
requirements and periodic funding
requirements.
Project document updates: The project document updates consists of risk register, cost estimates
and project schedule.
Answer option B is incorrect. Scope baseline is an input to the determine budget process.
Currently there are no comments in this discussion, be the first to comment!