Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 9 Question 88 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 88
Topic #: 9
[All PMI-RMP Questions]

After completing the sprint on an agile project a team updates the risk burndown chart and notices that risk exposure has increased to levels that could negatively affect project completion. What should the risk manager do to return the project's risk exposure to an acceptable level?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Rosalia
5 hours ago
We need to prioritize risk mitigation stories for the next sprint.
upvoted 0 times
...

Save Cancel