Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 9 Question 70 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 70
Topic #: 9
[All PMI-RMP Questions]

When processing freight invoices for a project, the project manager notices the shipping costs exceeded the budget due to increased fuel costs. The risk manager included this risk in the project's contingency allowance. When reviewing the project budget execution reports, the project manager notices unused budget remaining in other closed tasks of the project that could cover the additional shipping costs.

What should the project manager do?

Show Suggested Answer Hide Answer
Suggested Answer: A, B, D

Contribute your Thoughts:

Melita
2 days ago
I think the project manager should process the freight invoices at higher shipping costs against the project's contingency allowance.
upvoted 0 times
...

Save Cancel