Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 9 Question 65 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 65
Topic #: 9
[All PMI-RMP Questions]

The risk manager for an IT project developing a software application has a major stakeholder concerned that the project will not conclude within the available funding. The risk manager found delays in the iterations and increments in the project's budget, potentially increasing the duration by two weeks.

What tools should the risk manager use to properly decide the risk of not finishing the project within the budget?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Jenise
1 days ago
I agree with Bong. Monte Carlo simulations can help assess the risk of not finishing within budget.
upvoted 0 times
...
Bong
4 days ago
I think the risk manager should use estimation and probability analysis tools.
upvoted 0 times
...

Save Cancel