Question #: 24
Topic #: 9
[All PMI-RMP Questions]

Tom is the project manager of the GGG project for his company. He is working with the project team on the Perform Qualitative Risk Analysis process. Tom is having the project team to review the project scope statement as an input to the qualitative risk analysis process. Why?

Show Suggested Answer Hide Answer
Suggested Answer: B