Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 8 Question 90 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 90
Topic #: 8
[All PMI-RMP Questions]

Product testing can be done in multiple ways. A few project team members suggest testing be done in a laboratory environment, whereas others recommend completing the analysis via simulation methods. The testing manager has consulted with a peer, who recommends undertaking testing using field trials. The testing manager consults with the risk manager to assess the risk involved in the testing.

Which tool should the risk manager consider for assessing the test risk?

Show Suggested Answer Hide Answer
Suggested Answer: D

Contribute your Thoughts:

Gail
8 hours ago
I think the risk manager should consider using Monte Carlo simulation.
upvoted 0 times
...

Save Cancel