Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 8 Question 82 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 82
Topic #: 8
[All PMI-RMP Questions]

A risk manager has completed a risk identification workshop tor a construction project. One of the project risks is the delay in the shipment of some materials from another country. The risk manager and their team have determined this risk's low probability and high impact score.

What kind of analysis was done to determine this?

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel