Deal of The Day! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 8 Question 76 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 76
Topic #: 8
[All PMI-RMP Questions]

During the weekly project meeting a risk manager identified new risks in the last sprint, which might impact the project cost by implementing mitigation plans. The sponsor and some project team members do not agree that those risks can impact the project cost.

What should the risk manager do to resolve the sponsor and project team members' concerns about risk identification?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Maurine
2 days ago
I think the risk manager should reinforce that the risk identification was done properly.
upvoted 0 times
...

Save Cancel