Cyber Monday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 8 Question 48 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 48
Topic #: 8
[All PMI-RMP Questions]

You are the project manager of the GHY Project for your company. You have completed the risk response planning with your project team. You now need to update the WBS. Why would the project manager need to update the WBS after the risk response planning process? Choose the best answer.

Show Suggested Answer Hide Answer
Suggested Answer: B

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel