BlackFriday 2024! Hurry Up, Grab the Special Discount - Save 25% - Ends In 00:00:00 Coupon code: SAVE25
Welcome to Pass4Success

- Free Preparation Discussions

PMI Exam PMI-RMP Topic 8 Question 14 Discussion

Actual exam question for PMI's PMI-RMP exam
Question #: 14
Topic #: 8
[All PMI-RMP Questions]

You are the project manager of the NNH Project. In this project you have created a contingency response that the schedule performance index should be less than 0.93. The NHH Project has a budget at completion of $945,000 and is 45 percent complete though the project should be 49 percent complete. The project has spent $455,897 to reach the 45 percent complete milestone. What is the project's schedule performance index?

Show Suggested Answer Hide Answer
Suggested Answer: C

Contribute your Thoughts:

Currently there are no comments in this discussion, be the first to comment!


Save Cancel